January 2024 has seen restoration and maintenance works progressing across Warren Shire’s vast road network. 

Recent activities have comprised heavy patching on several sections of the Oxley Highway (SH-11) including near Warren Golf Club, Industrial Access Road, and the Warren Airport.

Line marking has commenced on Carinda Road, Warren Road, Collie/Trangie Road, Nevertire-Bogan Road, Victoria Oval, and other urban roads in Warren Shire. 

Ongoing environmental assessment and final scoping are in progress for the Nevertire-Bogan Road Project. Guidepost work has commenced on Buckingguy Road (SR-5), Carinda Road (RR-333), and Marthaguy Road (RR-202). Grading work has commenced at Gunningbah Road (SR95).

Patching has been completed at Ellengerah Road (SR-64) to address bitumen bleeding, and pothole repairs are being executed at Buckingguy Road (SR-5).  


Upcoming Works: Heavy patching will continue on the Oxley Highway towards Nevertire, then onwards towards Collie.

Scheduled pothole repairs are planned for Shire and Regional roads.

Planning is continuing for Rehabilitation of Nevertire-Bogan Road (SR58), with a view of commencing construction by March 2024.

RMCC safety and routine inspections, including guideposts and slashing, are scheduled for Regional Roads and Oxley Highway.

Line marking is also slated for completion on regional and urban roads. 