Road Report - November 2022
28 November 2022
Recent Works
Traffic Control: Oxley Highway
Flood Work: Town.
Flood Work (Levee): Town.
Escort Vehicle: Oxley Highway
Patching: Carinda Road, Marthaguy Road and Oxley Highway.
Signs: Town.
Road Maintenance and Construction Schedule
Upcoming maintenance grading and rehabilitation works scheduled for November 2022 include:
- Heatherbrae Road, Cremorne Road, Dandaloo Road, Old Warren Road, Sullivans Road, Colane Road, Marra Road, Bundemar Road, Boss Lane, Wonbobbie Lane, Cullemburrawang Road and Gillendoon Road.
*Flood Damage Works Program being developed.
*Please note these have not changed from last month due to weather constraints.
Capital Works in Progress
- Construction of Segment 30 of Old Warren Road funded by variations of Fixing Local Roads Round 3 funding after cost savings.
- Investigation and design work for CBD Improvement Program.
- Warren Road reconstruction, including new culverts, widening of the road, and pavement rehabilitation. Culverts have been ordered and are expected to be delivered in January 2023.
- Rehabilitation of Segment 18 of Collie-Trangie Road funded by the REPAIR Program 2022/2023.
- Gravel re-sheeting of Old Warren Road, subject to use for Fixing Local Roads grant application contributions, and other priority roads including Colane Road, Buddabadah Road and Gradgery Lane.
- Reseals of local roads and town streets to commence in 2023, subject to use for Fixing Local Roads grant application contributions.